Sign up to receive notices about road closures and construction – Text CLEELUM to 91896
NOTE: All posted Construction schedules are subject to change as needed.
In Progress
First Street Downtown Revitalization Project – FINAL PHASE 3D
Map and Brochure
3-week Look Ahead Schedule
-
-
- ACI Contractors work a 4-10 M-TH work schedule. This means they will not actively work on Fridays unless necessary.
- Public Works has procured “OPEN DURING CONSTRUCTION” signage for businesses within the current construction zone. These will be posted to new locations as the project progresses.
- Due to overwhelming interest, the CEDA Beautification and Facade Grant opening date has been pushed back to Wednesday, May 1, 2024, to ensure maximum funding will be available to serve as many requests as possible this year. Contact Cle Elum Downtown Association for more info.
- Please exercise caution in construction zones, following local protocol and laws. Construction areas can be narrow and often have a greater potential for organic debris (gravel, rocks, dirt, etc.) as well as slower traffic that may cause additional travel time.
- REMINDER: Construction schedule is provided as a general notification and guideline. Many factors, including inclement weather, materials and other extenuating factors have the potential to alter the overall schedule have the potential to alter the overall schedule.
- Construction updates every Thursday:
-
PEOH to BULLITT (NORTH)
-
-
- Segmented Block Wall
- Beginning: Monday, April 15
- Estimated Completion: Thursday, April 25
- Irrigation Main
- Estimated Completion: Thursday, April 18
- Grading
- Beginning: Monday, April 15
- Estimated Completion: Thursday, April 25
- Curb and Gutter
- Beginning: Wednesday, April 24
- Pour: Monday, April 29 – April 30
- Segmented Block Wall
-
BULLITT to WRIGHT (NORTH)
-
-
- Sidewalk removal
- Beginning: Monday, April 29
- Dates are subject to change based on current site conditions
- Sidewalk removal
-
- Second Street Water Main Improvement Project – Projected to finish Spring 2024
-
- Look ahead Schedule
- All posted Construction schedules are subject to change as needed.
- April 23
- Second Street crossings will be paved from Short Ave Yakima Ave.
- April 24
- Second Street will be closed while crossings are paved from Yakima Ave to Montgomery Ave.
- Water service crossings from Oakes Ave to Stafford Ave with road closures, detours and intermittent water shut offs
- April 25
- Second Street will be closed until Friday May 3, while crossings are paved from Oakes Ave to Stafford Ave per WADOT since that portion of roadway is state highway.
- Homeowners will still have access to their homes, along with emergency vehicles, USE CAUTION! Closed To Through Traffic.
- April 26
- No work performed
- April 29
- Water connection on Second Street Hill, behind Guardrail. Traffic Detours will be applied
- Replace Sidewalk panels
- April 30
- Tie in Stafford Ave North, Traffic Detours applied
- May 1
- Tie in Stafford Ave South. Traffic Detours will be applied
- May 2- May 3:
-
- Paving from Ronald Ave east to Oakes Ave
-
-
Upcoming…
- Second Street Pathway Project – Bid to open 5/23/2024
- Second Street Pathway is a 10-foot-wide asphalt pathway that can be used for bikes and pedestrians alike! Each intersection will have a concrete bulb out added.
- Full Project Plans and Engineering – Stafford Ave to Short Ave
- The first 5 blocks plans & engineering – Stafford Ave to Wright Ave
- Timeline for the first 5 blocks – Stafford Ave to Wright Ave:
Advertise for bids 5/9/2024 Bid Opening 5/23/2024 Award Construction Contract 5/28/2024 Preconstruction Meeting 6/20/2024 Notice to Proceed – Construction begins 6/24/2024 First 5 blocks – Construction Completion 8/26/2024
UKC Community Recreation Center – Pending
-
- Project information located here: recreationukc.org
- Notice of Application and Environmental Review – Comment Period